EPC project of 3 × 1080m3 blast furnace capacity expansion of 1380m3 blast furnace of Shanxi Gaoyi Iron and Steel Co., Ltd
Project introduction: the sintering machine started construction in December 2016, entered the single unit commissioning stage in August 2017, and put into operation smoothly in September. The blast furnace started construction in September 2016 and was put into operation smoothly in October 2017.
Contract scope: the project content includes civil engineering and installation engineering, refractory masonry construction, thermal insulation and anti-corrosion construction, electrical, instrumentation and automation engineering general contracting.